Church Reconstruction Timeline

Here is an expected timeline for the Church Font Project, from the TGI Construction Company:

  • Electrician should complete his work by Tuesday (of last week).
  • Drywall was scheduled to begin Wednesday, July 28th.
  • Storefront Metal for new glazing to be installed upon completion of drywall, approximately August 4th.
  • Upon installation of the metal, the glass and doors will be ordered.
  • Wood trim will also begin to be installed once the drywall is complete.
  • Aqua Link was scheduled to begin digging the area for the Baptismal Font mid next week.
  • We have ordered the floor tile and expect it to be here in approximately 2 weeks. (The original tile we selected months ago is no longer available, and we had to select new tile, which created a delay.)